A generator load bank test involves a series of examination and assessments on your diesel generator to ensure that it will function optimally when you need it most.
Generator load bank test report.
Generally speaking you ll need to perform a weekly inspection and a monthly load test on your epss 8 4 1.
It verifies that all primary components of the generator set are in proper working condition.
6 4 4 1 1 2 specifies that the 10 second criterion does not apply during the monthly testing of the generator.
In more detail the process occurs in this manner.
A load bank test ensures that your generator will run property when it s needed so that you can fully depend on it during an emergency situation.
The generator is then step loaded with the load bank until the desired load level is reached.
Load bank testing for two continuous hours each year.
2 in lieu of nfpa 110 5 13 2 3 h i hook up the dry type load bank to generator and perform a stepped load test on the generator at 25 50 80 and 100 of the nameplate kw rating of the generator.
The key to a proper load bank test is that it tests your generator at its full kilowatt kw output rating.
Can the generator load bank test be combined to meet the 36 month test as well as the 4 hour load test.
The equipment used to conduct a load bank test produces artificial loads on the generator by bringing the engine to an appropriate operating temperature and pressure level.
It ensures capability and battery autonomy as well as making sure that all the generator s primary components are in proper working order under loaded conditions.
If a generator fails the monthly test it should be operated under a load supplied by a load bank i e.
During this two hour period the unit should be operated as follows.
Each step to last fifteen 15 minutes record engine and generator data as detailed later in this section.
At 25 of the nameplate kilowatt rating for 30 minutes.
A generator load bank test is a timed process and the device gradually increases the load so that the generator s performance at different levels of outputs can be measured.
At 50 of the nameplate kilowatt rating for 30 minutes.
Each time the load is increased the test measures and records the key indicators of generator s performance like its ability to handle an increase in the load and to.
After the test the technician removes the load bank load first and transfers all switches back to the normal position before allowing the generator to cool down according to manufacturer guidelines.
The testing for an annual load bank test and the triennial exercise may be combined according to nfpa 110 2010.